We stick to the descriptions of our initial roadmap. So far the design is still valid. However, based on our experience after M8.1 and M8.2 we must admit that we underestimated M8.3. Especially the test fixtures are more laborsome than we anticipated. We can still not use cargo test
for our SGX enclave code, so we have to wrap everything with custom commands and mocking is only partially possible leading to more end2end tests which are harder to debug. Moreover, we became aware of #208 which needs to be fixed.
Our initial estimate for M8.3 was CHF 39'200.- but we have to adjust to 48'400 CHF (+23%).
We currently have 1.3 FTE reserved for this and intend to deliver within 9 weeks after this motion passes.
DOT moving average MA(25)@1day today is 32.0 USDT on binance
USDT is 0.9302 CHF according to coinmarketcap
along previous proposals, we'd add a 10% premium for volatility risk.
We therefore request 48400*1.1/32.0/0.9302 = 1788.59 DOT
external reviews of our previous milestones M8.1 and M8.2: review1, review2
SubSquare is a project that is working on a new technology called SubstraTEE. They have encountered some challenges with their latest milestone, M8.3, which is taking longer than expected. They need more time and money to complete it. They estimate that it will cost 48,400 CHF and take 9 weeks to complete. They are requesting 1788.59 DOT to cover the costs. They have received reviews from external sources for their previous milestones, M8.1 and M8.2, and they encourage people to tip the reviewers.